Battlefield Road/Route 65 Interchange Reconstruction Project Update April 6
April 03, 2015
Battlefield Road/Route 65 Interchange Reconstruction Project
Update for Week of April 6, 2015
-
Route 65 traffic scheduled to shift away from median at Battlefield Road on Monday evening, April 6
-
Southbound Route 65 lane closings needed during weekend of April 11
Work Scheduled:
-
Building bridge column in median of Route 65
-
Building retaining walls and bridge supports on either side of Route 65 at Battlefield Road
-
Pouring concrete for southbound Route 65 auxiliary lane between Sunshine Street and Battlefield Road
-
Building retaining wall on southwest corner of Battlefield Road and Route 65
-
Installing storm drains along Battlefield Road on either side of Route 65
Traffic Impacts:
-
Route 65 traffic scheduled to be shifted AWAY from median after 7 p.m. Monday, April 6. Lane shift will remain in place until late August.
-
Route 65 speed limit reduced to 50 mph at Battlefield Road.
-
Southbound right-lane on Route 65 closed between Sunshine Street and Battlefield Road. Work hours: daytime hours Saturday and Sunday, April 11-12.
-
TRAFFIC CONGESTION on Battlefield Road at Route 65. One lane open in each direction in diverging diamond traffic pattern
-
Crews and equipment entering and leaving work areas
(Weather or construction delays could alter the work schedule.)
Project Summary:
-
Replace Battlefield Road bridge over Route 65 one-half at a time
-
Convert interchange to a Diverging Diamond configuration
-
Build northbound and southbound auxiliary lanes on Route 65 to connect Sunshine Street and Battlefield Road ramps
-
Install new traffic signal at Battlefield Road and Woodstock Avenue
Project information with live camera view
Prime Contractor: Hartman and Company, Inc., Springfield
Completion Date: September 2015
Total Project Cost: $12.5 million.
Partnership Project: City of Springfield, Greene County, Ozarks Transportation Organization, Jack Henry & Associates, Justice Jewelers and McLean Enterprises, Inc.