Battlefield Road/Route 65 Interchange Reconstruction Project Update Dec 12
December 12, 2014 10:37 AM
Battlefield Road/Route 65 Interchange Reconstruction Project
Update for Week of Dec. 15, 2014
-
Short-term traffic stops on the northbound on ramp and southbound off ramp
-
Breaking rock along northbound on ramp ‘round the clock
Work Scheduled:
-
Breaking rock ‘round the clock and excavating dirt along the northbound on ramp (northeast ramp)
-
Hauling rock and dirt from southbound off ramp (northwest ramp) to areas along southbound Route 65 for future auxiliary lane
-
Hauling rock and dirt to southbound on ramp (southwest ramp)
Traffic Impacts:
-
Short-term traffic stops on northbound on ramp (northeast ramp) and southbound off ramp (northwest ramp)
-
Right shoulder closed along southbound Route 65 at times
-
No lane closings planned on Battlefield Road or on Route 65
-
Be alert for trucks entering and leaving work areas
(Weather or construction delays could alter the work schedule.)
Project Summary:
-
Replace Battlefield Road bridge over Route 65
-
Convert interchange to a Diverging Diamond configuration
-
Build northbound and southbound auxiliary lanes on Route 65 to connect Sunshine Street and Battlefield Road ramps
-
Install new traffic signal at Battlefield Road and Woodstock Avenue
Project information with live camera view
Prime Contractor: Hartman and Company, Inc., Springfield
Completion Date: September 2015
Total Project Cost: $12.5 million.
Partnership Project: City of Springfield, Greene County, Ozarks Transportation Organization, Jack Henry & Associates, Justice Jewelers and McLean Enterprises, Inc.