Battlefield Road/Route 65 Interchange Reconstruction Project

Update for Week of Dec. 8, 2014

  • Large dump trucks entering and leaving work areas with traffic
  • Excavating rock and dirt near ramps

Work Scheduled:  

  • Excavating rock and dirt along the ramps in various locations
  • Excavating rock/dirt and extended drain pipes along the southbound lanes of Route 65 between Sunshine Street and Battlefield Road
  • Relocating utilities in various locations

Traffic Impacts: 

  • No lane closings planned on Battlefield Road or on Route 65
  • Be alert for trucks entering and leaving work areas
  • Crews and equipment close to traffic

(Weather or construction delays could alter the work schedule.)

Project Summary:

  • Replace Battlefield Road bridge over Route 65
  • Convert interchange to a Diverging Diamond configuration
  • Build northbound and southbound auxiliary lanes on Route 65 to connect Sunshine Street and Battlefield Road ramps
  • Install new traffic signal at Battlefield Road and Woodstock Avenue

Project information with live camera view

Prime Contractor: Hartman and Company, Inc., Springfield

Completion Date: September 2015

Total Project Cost: $12.5 million.

Partnership Project: City of Springfield, Greene County, Ozarks Transportation Organization, Jack Henry & Associates, Justice Jewelers and McLean Enterprises, Inc.

 