Battlefield Road/Route 65 Interchange Reconstruction Project Update June 1
May 29, 2015 01:58 PM
Battlefield Road/Route 65 Interchange Reconstruction Project
Update for Week of June 1, 2015
-
Southbound on ramp from Battlefield Road to U.S. Route 65 CLOSED at night for paving for a couple of nights
Work Scheduled:
-
Rebuilding and widening southbound on ramp from Battlefield Road to Route 65
-
Pouring concrete for a bridge approach on either side of the new Battlefield Road bridge over Route 65
-
Building curb and gutter on the southwest corner of the interchange along Battlefield Road
Traffic Impacts:
-
NIGHT WORK: Southbound on ramp from Battlefield Road to Route 65 CLOSED at night. Work hours: 7 p.m. to 6 a.m. Ramp open during daytime hours.
-
All six lanes of Route 65 shifted AWAY from median at Battlefield Road
-
TRAFFIC CONGESTION on Battlefield Road at Route 65. One lane open in each direction in diverging diamond traffic pattern.
-
Lane closings possible at times on Route 65 during lower traffic volume times
-
Route 65 speed limit reduced to 50 mph during lane closings
-
Crews and equipment entering and leaving work areas
(Weather or construction delays could alter the work schedule.)
Project Summary:
-
Replace Battlefield Road bridge over Route 65 one-half at a time
-
Convert interchange to a Diverging Diamond configuration
-
Build northbound and southbound auxiliary lanes on Route 65 to connect Sunshine Street and Battlefield Road ramps
-
Install new traffic signal at Battlefield Road and Woodstock Avenue
Project information with live camera view
Prime Contractor: Hartman and Company, Inc., Springfield
Completion Date: September 2015
Total Project Cost: $12.5 million.
Partnership Project: City of Springfield, Greene County, Ozarks Transportation Organization, Jack Henry & Associates, Justice Jewelers and McLean Enterprises, Inc.