Skip to Main Content

Battlefield Road/Route 65 Interchange Reconstruction Project Update June 15

June 12, 2015 03:08 PM

Battlefield Road/Route 65 Interchange Reconstruction Project

Update for Week of June 15, 2015

  • Nighttime lane closings possible on Battlefield Road at U.S. Route 65
  • Battlefield Road scheduled to CLOSE between Route 65 and Woodstock Drive Week of June 21 until June 29

Work Scheduled: 

  • Pouring concrete for driving surface on the new Battlefield Road bridge over Route 65
  • Rebuilding and widening northbound off ramp from Route 65 to Battlefield Road
  • Rebuilding and widening southbound on ramp from Battlefield Road to Route 65
  • Pouring concrete for a bridge approach on either side of the new Battlefield Road bridge over Route 65
  • Building curb and gutter on the southwest corner of the interchange along Battlefield Road

Traffic Impacts: 

  • Nighttime lane closings possible on Battlefield Road at Route 65
  • Battlefield Road CLOSING between Route 65 and Woodstock Drive sometime during the week of June 21 until June 29
  • Northbound Route 65 off ramp to Battlefield Road CLOSED until Monday, June 29
  • All six lanes of Route 65 shifted AWAY from median at Battlefield Road
  • TRAFFIC CONGESTION on Battlefield Road at Route 65. One lane open in each direction in diverging diamond traffic pattern.
  • Lane closings possible at times on Route 65 during lower traffic volume times
  • Route 65 speed limit reduced to 50 mph during lane closings
  • Crews and equipment entering and leaving work areas

(Weather or construction delays could alter the work schedule.)

Project Summary

  • Replace Battlefield Road bridge over Route 65 one-half at a time
  • Convert interchange to a Diverging Diamond configuration
  • Build northbound and southbound auxiliary lanes on Route 65 to connect Sunshine Street and Battlefield Road ramps
  • Install new traffic signal at Battlefield Road and Woodstock Avenue

Project information with live camera view

Prime Contractor:Hartman and Company, Inc., Springfield

Completion Date:September 2015

Total Project Cost:$12.5 million.

Partnership Project:City of Springfield, Greene County, Ozarks Transportation Organization, Jack Henry & Associates, Justice Jewelers and McLean Enterprises, Inc.

 

Back

 

© 2024 City of Springfield

 CityLogo_VERT_1Color_300dpi   Logo

 

 

 

close (X)