Battlefield Road/Route 65 Interchange Reconstruction Project Update Mar 30
March 27, 2015 10:32 AM
Battlefield Road/Route 65 Interchange Reconstruction Project
Update for Week of March 30, 2015
-
Route 65 traffic scheduled to shift away from median for bridge work late in the week
Work Scheduled:
-
Building retaining walls and bridge supports on either side of Route 65 at Battlefield Road
-
Shifting Route 65 traffic away from median for bridge work late in the week
-
Removing southbound outside shoulder of Route 65 to make way for new auxiliary lane
-
Installing storm drains along Battlefield Road near Woodstock Avenue
Traffic Impacts:
-
Route 65 traffic scheduled to be shifted AWAY from median late in the week. Weather or construction delays could postpone the traffic shift until the week of April 6.
-
Lane closings on Route 65 underneath Battlefield Road during lower traffic volume times. Work hours: 9 a.m. to 3 p.m.
-
Southbound right lane closed at times on Route 65 between Sunshine Street and Battlefield Road. Lane closings possible between 9 a.m. and 3 p.m.
-
TRAFFIC CONGESTION on Battlefield Road at Route 65. One lane open in each direction in diverging diamond traffic pattern
-
Crews and equipment entering and leaving work areas
(Weather or construction delays could alter the work schedule.)
Project Summary:
-
Replace Battlefield Road bridge over Route 65 one-half at a time
-
Convert interchange to a Diverging Diamond configuration
-
Build northbound and southbound auxiliary lanes on Route 65 to connect Sunshine Street and Battlefield Road ramps
-
Install new traffic signal at Battlefield Road and Woodstock Avenue
Project information with live camera view
Prime Contractor: Hartman and Company, Inc., Springfield
Completion Date: September 2015
Total Project Cost: $12.5 million.
Partnership Project: City of Springfield, Greene County, Ozarks Transportation Organization, Jack Henry & Associates, Justice Jewelers and McLean Enterprises, Inc.