Battlefield Road/Route 65 Interchange Reconstruction Project Update May 4
April 30, 2015 02:33 PM
Battlefield Road/Route 65 Interchange Reconstruction Project
Update for Week of May 4, 2015
-
Southbound On Ramp from Battlefield Road to Route 65 Scheduled to CLOSE Week of May 4 until week of May 18
-
Southbound Off Ramp from Route 65 to Battlefield Road scheduled to reopen early in week
Work Scheduled:
-
Complete work on rebuilding and widening southbound Route 65 off ramp to Battlefield Road
-
When southbound off ramp is complete, work will begin to rebuild and widen southbound on ramp from Battlefield Road to Route 65
-
Grading rock and dirt for new northbound Route 65 auxiliary lane between Battlefield Road and Route 65
-
Pouring concrete for approach pavement to new half of Battlefield Road bridge over Route 65
-
Relocating utilities along Battlefield Road near Woodstock Avenue
-
Hauling rock and dirt to areas on southwest corner of interchange
Traffic Impacts:
-
Southbound on ramp from Battlefield Road to Route 65 scheduled to CLOSE week of May 4 until week of May 18
-
Southbound off ramp to Battlefield Road scheduled to REOPEN early in week before southbound on ramp is closed
-
Northbound right-lane of Route 65 closed between Battlefield Road and Sunshine Street during lower traffic volume times
-
Route 65 speed limit reduced to 50 mph during lane closings
-
All six lanes of Route 65 shifted AWAY from median at Battlefield Road
-
TAFFIC CONGESTIONon Battlefield Road at Route 65. One lane open in each direction in diverging diamond traffic pattern.
-
Crews and equipment entering and leaving work areas
(Weather or construction delays could alter the work schedule.)
Project Summary:
-
Replace Battlefield Road bridge over Route 65 one-half at a time
-
Convert interchange to a Diverging Diamond configuration
-
Build northbound and southbound auxiliary lanes on Route 65 to connect Sunshine Street and Battlefield Road ramps
-
Install new traffic signal at Battlefield Road and Woodstock Avenue
Project information with live camera view
Prime Contractor: Hartman and Company, Inc., Springfield
Completion Date: September 2015
Total Project Cost: $12.5 million.
Partnership Project: City of Springfield, Greene County, Ozarks Transportation Organization, Jack Henry & Associates, Justice Jewelers and McLean Enterprises, Inc.