Build new access roads on either side of Chestnut Expressway
Phase One - June 2016-Oct. 2016
-
Build access road to businesses north of Chestnut Expressway
-
Build part of temporary bypass north of Chestnut Expressway across railroad tracks
-
Relocate utility lines
-
Traffic Impacts:
-
Chestnut Expressway CLOSED at night periodically for utility crossings. Work hours: 9 p.m. to 6 a.m.
Phase Two - Nov. 2016-Late 2017:
-
Build railroad bridge over Burlington Northern-Santa Fe tracks
-
Improve intersection of Ingram Mill Road & Chestnut Expressway and add traffic signal
-
Build access road south of Chestnut Expressway west of Ingram Mill Road
-
Traffic Impacts:
-
Chestnut Expressway traffic shifted to temporary bypass
-
Two westbound lanes and one eastbound lane open on bypass
-
Significant traffic delays expected on Chestnut Expressway
-
Drivers urged to find alternate routes
Construction: Summer 2016-Late 2017
Estimated Total Cost: $14.8 million
Partnership Project: City of Springfield, Greene County, Burlington Northern-Santa Fe Railroad and MoDOT