Skip to Main Content

Construction

TypeAddressDescriptionDetails
ROADWORK S PARKMONT AVE CLOSED AT USE ALT ROUTE
Thu Apr 17 09:16:26 CDT 2025
Through Lane Closed
Starting on 4-17-2025, City crews will be closing Parkmont between Katella and Primrose for sewer repairs. Work is scheduled to be completed by 5pm on 4-18-2025.
17-Apr-2025 14:16:26
ROADWORK GRANT AVE SB / AT NORTON RD
Thu Apr 17 09:11:13 CDT 2025
Right Lane Closed
City contractors have a lane drop on Grant south of Norton for utility improvements.
17-Apr-2025 14:11:13
ROADWORK ROADWORK BE PREPARED TO STOP
Tue Apr 15 11:38:11 CDT 2025

Starting on 4-16-2025, City contractors will be flagging traffic on Briar between National and Palmer due to construction. Work is scheduled to be completed on 4-18-2025.
15-Apr-2025 16:38:11
ROADWORK FREMONT AVE NB / PAST BRIAR ST
Tue Apr 15 11:38:03 CDT 2025

Starting on 4-16-2025, City contractors will be doing street resurfacing on Fremont between Lark and Briar. Work is scheduled to be completed by 4-18-2025.
15-Apr-2025 16:38:03
ROADWORK ROADWORK BE PREPARED TO STOP
Tue Apr 15 11:37:51 CDT 2025

Starting on 4-22-2025, City contractors will be resurfacing Grand between Stewart and Chadwick. Work is scheduled to be completed by 4pm on 4-22-2025.
15-Apr-2025 16:37:51
ROADWORK ROADWORK BE PREPARED TO STOP
Tue Apr 15 11:37:43 CDT 2025

Starting on 4-21-2025, City contractors will be resurfacing Oak Grove between Cherry and Sunshine. Work is scheduled to be completed by 5pm on 4-21-2025.
15-Apr-2025 16:37:43
ROADWORK ROADWORK BE PREPARED TO STOP
Tue Apr 15 07:49:14 CDT 2025

Starting on 4-21-2025, City crews will be closing the southbound lane of Lone Pine between Galloway and Republic for road repairs. Work is scheduled to be completed by 4pm on 4-23-2025.
15-Apr-2025 12:49:14
ROADWORK N MISSOURI AVE CLOSED AT USE ALT ROUTE
Tue Apr 15 07:48:53 CDT 2025
Through Lane Closed
Starting on 4-14-2025, City crews will be closing Missouri between Webster and Scott for sewer repairs. Work is scheduled to be completed by 5pm on 4-18-2025.
15-Apr-2025 12:48:53
ROADWORK REPUBLIC ST WB / PAST SCENIC AVE
Thu Apr 10 13:11:11 CDT 2025
Right Lane Closed
Starting on 4-14-2025, City crews will be closing the outside lane of Republic between Scenic and Homewood for street repairs. Work is scheduled to be completed by 6am on 4-24-2025.
10-Apr-2025 18:11:11
ROADWORK FRISCO AVE CLOSED AT USE ALT ROUTE
Tue Apr 08 08:22:02 CDT 2025
Through Lane Closed
Starting on 4-9-2025, City contractors will be closing Frisco Ln between Jefferson and Robberson for bridge improvements. Work is scheduled to be completed by 12am on 11-28-2025.
08-Apr-2025 13:22:02
ROADWORK CAMPBELL AVE NB / PAST OLIVE ST
Thu Apr 03 11:51:00 CDT 2025
Right Lane Closed
Starting on 4-9-2025, City contractors will be closing the #2 lane of northbound Campbell between Olive and Phelps for utility improvements. Work is scheduled to be completed by 12am on 4-23-2025.
03-Apr-2025 16:51:00
ROADWORK N BOONVILLE AVE CLOSED AT USE ALT ROUTE
Thu Apr 03 11:50:53 CDT 2025
Through Lane Closed
Starting on 4-10-2025, City contractors will be closing Boonville at Water for utility improvements. Work is scheduled to be completed by 12am on 4-24-2025.
03-Apr-2025 16:50:53
ROADWORK ROADWORK E GALLOWAY ST USE ALT ROUTE
Tue Jan 21 09:55:39 CST 2025
Through Lane Closed
Starting on 1-22-2025, City contractors will be closing westbound Galloway between Lone Pine and Luster for construction. Work is scheduled to be completed on 4-30-2025.
21-Jan-2025 15:55:39
MoDOT Workzone - Expect Delays US 65 S CHRISTIAN
Expect delays due to Work Zone
US-65 Southbound (CHRISTIAN County)

NEW PAVEMENT CONSTRUCTION is scheduled from 13-NOV-2023 to 01-NOV-2025. Work will be conducted on weekdays only between the hours of 06:00 AM and 04:00 PM.

21-Apr-2025 17:27:08
MoDOT Workzone - Expect Delays US 65 N CHRISTIAN
Expect delays due to Work Zone
US-65 Northbound (CHRISTIAN County)

NEW PAVEMENT CONSTRUCTION is scheduled from 13-NOV-2023 to 01-NOV-2025. Work will be conducted on weekdays only between the hours of 06:00 AM and 04:00 PM.

21-Apr-2025 17:27:08
MoDOT Workzone - Closure US 60 E GREENE
Road closed due to VEHICLE CRASH
US-60 Eastbound (GREENE County)

Impact reported at 12:05 PM on 04/21/2025. Closure estimated to last 0.5 hour(s).

NOTE: INJURY ACCIDENT US 60 EB PAST MAIN ST USE ALT ROUTE US 60 EB 2 LEFT LANES CLOSED EST. CLEARANCE TIME: 12:35 PM (-93463967,37125506)
21-Apr-2025 17:27:10
MoDOT Workzone - Future Project RP IS44W TO MO266E E GREENE
Future Work Zone
Ramp IS44W TO MO266E Eastbound (GREENE County)

CONCRETE OVERLAY is scheduled from 22-APR-2025 to 24-APR-2025. Work will be conducted on weekdays only between the hours of 08:00 AM and 04:00 PM.

21-Apr-2025 17:27:10
MoDOT Workzone - Future Project RT PP S GREENE
Future Work Zone
Route PP Southbound (GREENE County)

ROAD MIX OVERLAY is scheduled from 22-APR-2025 to 25-APR-2025. Work will be conducted on weekdays only between the hours of 06:00 AM and 04:30 PM.

21-Apr-2025 17:27:10
MoDOT Workzone - Future Project RT J S GREENE
Future Work Zone
Route J Southbound (GREENE County)

CORE DRILLING is scheduled from 28-APR-2025 to 01-MAY-2025. Work will be conducted on weekdays only between the hours of 08:00 AM and 04:00 PM.

21-Apr-2025 17:27:09
MoDOT Workzone - Future Project RT J N GREENE
Future Work Zone
Route J Northbound (GREENE County)

CORE DRILLING is scheduled from 28-APR-2025 to 01-MAY-2025. Work will be conducted on weekdays only between the hours of 08:00 AM and 04:00 PM.

21-Apr-2025 17:27:09
MoDOT Workzone - Expect Delays CST GLENSTONE AVE N GREENE
Expect delays due to Work Zone
GLENSTONE AVE Northbound (GREENE County)

BRIDGE MAINTENANCE is scheduled from 07-APR-2025 to 28-APR-2025. Work will be conducted on weekdays only between the hours of 08:00 PM and 06:00 AM.

21-Apr-2025 17:27:09
MoDOT Workzone - Expect Delays CST GLENSTONE AVE S GREENE
Expect delays due to Work Zone
GLENSTONE AVE Southbound (GREENE County)

BRIDGE MAINTENANCE is scheduled from 07-APR-2025 to 28-APR-2025. Work will be conducted on weekdays only between the hours of 08:00 PM and 06:00 AM.

21-Apr-2025 17:27:09
MoDOT Workzone - Expect Delays CST JAMES RIVER FRWY W GREENE
Expect delays due to Work Zone
JAMES RIVER FRWY Westbound (GREENE County)

BRIDGE MAINTENANCE is scheduled from 04-MAR-2025 to 04-MAY-2025. Work will be conducted 7 days a week between the hours of 06:00 AM and 07:00 PM.

21-Apr-2025 17:27:09
MoDOT Workzone - Expect Delays RP MO744 TO US65S S GREENE
Expect delays due to Work Zone
Ramp MO744 TO US65S Southbound (GREENE County)

RESURFACING PAVEMENT is scheduled from 27-OCT-2024 to 01-MAY-2025. Work will be conducted on weekdays and Saturdays"); between the hours of 08:00 PM and 06:00 AM.

21-Apr-2025 17:27:09
MoDOT Workzone - Expect Delays RP US65N TO MO744 E GREENE
Expect delays due to Work Zone
Ramp US65N TO MO744 Eastbound (GREENE County)

RESURFACING PAVEMENT is scheduled from 27-OCT-2024 to 01-MAY-2025. Work will be conducted on weekdays and Saturdays"); between the hours of 08:00 PM and 06:00 AM.

21-Apr-2025 17:27:09
MoDOT Workzone - Expect Delays RT J S GREENE
Expect delays due to Work Zone
Route J Southbound (GREENE County)

CORE DRILLING is scheduled from 21-APR-2025 to 24-APR-2025. Work will be conducted on weekdays only between the hours of 08:00 AM and 04:00 PM.

21-Apr-2025 17:27:09
MoDOT Workzone - Expect Delays RT J N GREENE
Expect delays due to Work Zone
Route J Northbound (GREENE County)

CORE DRILLING is scheduled from 21-APR-2025 to 24-APR-2025. Work will be conducted on weekdays only between the hours of 08:00 AM and 04:00 PM.

21-Apr-2025 17:27:09
MoDOT Workzone - Expect Delays RP MO744 TO US65N N GREENE
Expect delays due to Work Zone
Ramp MO744 TO US65N Northbound (GREENE County)

PAVEMENT MARKING is scheduled from 30-OCT-2024 to 01-MAY-2025. Work will be conducted on weekdays and Saturdays"); between the hours of 08:00 PM and 06:00 PM.

21-Apr-2025 17:27:09
MoDOT Workzone - Expect Delays MO 125 S GREENE
Expect delays due to Work Zone
MO-125 Southbound (GREENE County)

NEW PAVEMENT CONSTRUCTION is scheduled from 10-MAR-2025 to 22-MAY-2026. Work will be conducted on weekdays only. Traffic may be impacted 24 hours a day.

21-Apr-2025 17:27:09
MoDOT Workzone - Expect Delays MO 125 N GREENE
Expect delays due to Work Zone
MO-125 Northbound (GREENE County)

NEW PAVEMENT CONSTRUCTION is scheduled from 10-MAR-2025 to 22-MAY-2026. Work will be conducted on weekdays only. Traffic may be impacted 24 hours a day.

21-Apr-2025 17:27:09
MoDOT Workzone - Expect Delays MO 744 W GREENE
Expect delays due to Work Zone
MO-744 Westbound (GREENE County)

RESURFACING PAVEMENT is scheduled from 10-JUN-2024 to 31-JUL-2025. Work will be conducted on weekdays only between the hours of 06:00 AM and 06:00 PM.

21-Apr-2025 17:27:08
MoDOT Workzone - Expect Delays MO 744 E GREENE
Expect delays due to Work Zone
MO-744 Eastbound (GREENE County)

RESURFACING PAVEMENT is scheduled from 10-JUN-2024 to 31-JUL-2025. Work will be conducted on weekdays only between the hours of 06:00 AM and 06:00 PM.

21-Apr-2025 17:27:08
MoDOT Workzone - Expect Delays US 65 N GREENE
Expect delays due to Work Zone
US-65 Northbound (GREENE County)

BRIDGE MAINTENANCE is scheduled from 14-APR-2025 to 21-APR-2025. Work will be conducted on weekdays only between the hours of 07:00 AM and 05:00 PM.

21-Apr-2025 17:27:08
MoDOT Workzone - Expect Delays US 60 E GREENE
Expect delays due to Work Zone
US-60 Eastbound (GREENE County)

PAVEMENT REPAIR is scheduled from 31-MAR-2025 to 02-MAY-2025. Work will be conducted on weekdays only between the hours of 07:00 PM and 06:00 AM.

21-Apr-2025 17:27:08
MoDOT Workszone - Possible Delays CRD VALLEY WATER MILL RD E GREENE
Possible delays due to Work Zone
CRD-VALLEY WATER MILL RD Eastbound (GREENE County)

BRIDGE MAINTENANCE is scheduled from 21-APR-2025 to 24-APR-2025. Work will be conducted on weekdays only between the hours of 08:00 AM and 04:00 PM.

21-Apr-2025 17:27:08
MoDOT Workzone - Expect Delays US 60 E GREENE
Expect delays due to Work Zone
US-60 Eastbound (GREENE County)

RESURFACING PAVEMENT is scheduled from 14-APR-2025 to 17-MAY-2025. Work will be conducted on weekdays only between the hours of 08:00 PM and 06:00 AM.

21-Apr-2025 17:27:08
MoDOT Workzone - Expect Delays US 60 W GREENE
Expect delays due to Work Zone
US-60 Westbound (GREENE County)

RESURFACING PAVEMENT is scheduled from 14-APR-2025 to 17-MAY-2025. Work will be conducted on weekdays only between the hours of 08:00 PM and 06:00 AM.

21-Apr-2025 17:27:08
MoDOT Workzone - Expect Delays RT CC W GREENE
Expect delays due to Work Zone
Route CC Westbound (GREENE County)

ROAD MIX OVERLAY is scheduled from 21-APR-2025 to 25-APR-2025. Work will be conducted on weekdays only between the hours of 06:00 AM and 04:30 PM.

21-Apr-2025 17:27:08
MoDOT Workzone - Expect Delays IS 44 W GREENE
Expect delays due to Work Zone
I-44 Westbound (GREENE County)

NEW PAVEMENT CONSTRUCTION is scheduled from 10-MAR-2025 to 21-MAY-2027. Work will be conducted on weekdays and Saturdays between the hours of 08:00 PM and 06:00 AM.

21-Apr-2025 17:27:08
MoDOT Workzone - Expect Delays IS 44 E GREENE
Expect delays due to Work Zone
I-44 Eastbound (GREENE County)

NEW PAVEMENT CONSTRUCTION is scheduled from 10-MAR-2025 to 21-MAY-2027. Work will be conducted on weekdays and Saturdays between the hours of 08:00 PM and 06:00 AM.

21-Apr-2025 17:27:08
MoDOT Workzone - Expect Delays IS 44 W GREENE
Expect delays due to Work Zone
I-44 Westbound (GREENE County)

NEW PAVEMENT CONSTRUCTION is scheduled from 21-APR-2025 to 21-OCT-2025. Work will be conducted 7 days a week. Traffic may be impacted 24 hours a day.

21-Apr-2025 17:27:08
MoDOT Workzone - Expect Delays RP US65S TO MO744 W GREENE
Expect delays due to Work Zone
Ramp US65S TO MO744 Westbound (GREENE County)

PAVEMENT MARKING is scheduled from 30-OCT-2024 to 01-MAY-2025. Work will be conducted on weekdays and Saturdays"); between the hours of 08:00 AM and 06:00 AM.

21-Apr-2025 17:27:07
MoDOT Workzone - Expect Delays CST CHESTNUT EXPY W GREENE
Expect delays due to Work Zone
CHESTNUT EXPY Westbound (GREENE County)

SIDEWALK/ADA IMPROVEMENTS is scheduled from 16-DEC-2024 to 30-JUN-2026. Work will be conducted on weekdays only. Traffic may be impacted 24 hours a day.

21-Apr-2025 17:27:07
MoDOT Workzone - Expect Delays CST CHESTNUT EXPY E GREENE
Expect delays due to Work Zone
CHESTNUT EXPY Eastbound (GREENE County)

SIDEWALK/ADA IMPROVEMENTS is scheduled from 16-DEC-2024 to 30-JUN-2026. Work will be conducted on weekdays only. Traffic may be impacted 24 hours a day.

21-Apr-2025 17:27:07
MoDOT Workzone - Expect Delays LP 44 W GREENE
Expect delays due to Work Zone
LP-44 Westbound (GREENE County)

SIDEWALK/ADA IMPROVEMENTS is scheduled from 16-DEC-2024 to 30-JUN-2026. Work will be conducted on weekdays only. Traffic may be impacted 24 hours a day.

21-Apr-2025 17:27:07
MoDOT Workzone - Expect Delays LP 44 E GREENE
Expect delays due to Work Zone
LP-44 Eastbound (GREENE County)

SIDEWALK/ADA IMPROVEMENTS is scheduled from 16-DEC-2024 to 30-JUN-2026. Work will be conducted on weekdays only. Traffic may be impacted 24 hours a day.

21-Apr-2025 17:27:07

© 2025 City of Springfield

 CityLogo_VERT_1Color_300dpi   Logo

 

 

 

close (X)