Northbound Route 65 expected to OPEN between Route 60 and Sunshine Street by late Saturday or Sunday night, Sept. 14-15
Work Scheduled:
-
Pour concrete for new northbound Route 65 pavement between Route 60 and Sunshine Street (paving should be complete by Thursday, Sept. 12)
-
Diamond-grind (smooth) new Route 65 pavement
-
Install guardrail in areas along Route 65
-
Pave shoulders in areas along Route 65
Traffic Impacts:
-
Northbound Route 65 scheduled to REOPEN between Route 60 and Sunshine Street by late Saturday or Sunday night, Sept. 14-15. Until then, northbound Route 65 remains CLOSED.
-
Eastbound Route 60-to-northbound Route 65 ramp closed
-
Westbound Route 60-to-northbound Route 65 ramp closed
-
Eastbound on ramp from Glenstone Avenue to Route 60 closed
-
Route 60 median crossovers closed between Route 65 and Greene County Route NN/J interchange east of Springfield
-
Night work:One southbound lane of Route 65 closed at times. Work hours: 8 p.m. to 6 a.m.
-
Temporary traffic signals in operation at Blackman Road/Battlefield Road and Greene County Route D/Route 125 intersections. Signals removed once closings of Route 65 are complete.
-
Signed detours during northbound Route 65 closings:
-
West detour: I-44 to eastbound Missouri Route 360 to eastbound U.S. Route 60 to southbound Route 65
-
East detour: I-44 to Missouri Route 125 to westbound U.S. 60 to southbound Route 65
(Weather or construction delays could alter the work schedule.)
Project Summary:
-
Sunday-Thursday, August 4-8 -- COMPLETE
-
All southbound lanes of Route 65 CLOSED between Sunshine Street and Battlefield Road
-
Southbound on ramp from Sunshine Street to Route 65 CLOSED
-
Southbound off ramp from Route 65 to Battlefield Road CLOSED
-
Thursday-Friday, August 8-16 -- COMPLETE
-
-
All southbound lanes of Route 65 CLOSED between Battlefield Road and Route 60
-
Southbound Route 65 OPEN between Sunshine Street and Battlefield Road, but reduced to one lane
-
Southbound on ramp from Battlefield Road to Route 65 CLOSED
-
Southbound Route 65-to-westbound Route 60 ramp CLOSED
All lanes of Route 65 open during the Labor Day holiday (Friday-Friday, August 16-September 6)
-
Friday-Friday, September 6-20 (All northbound Route 65 lanes could be open as early as Saturday or Sunday, Sept. 14 or 15)
-
All northbound lanes of Route 65 CLOSED between Route 60 and Sunshine Street
-
Eastbound Route 60-to-northbound Route 65 ramp CLOSED
-
Westbound Route 60-to-northbound Route 65 ramp CLOSED
-
Northbound off ramp from Route 65 to Battlefield Road CLOSED
-
Northbound on ramp from Battlefield Road to northbound Route 65 CLOSED
-
Northbound off ramp from Route 65 to Sunshine Street CLOSED
-
Eastbound on ramp from Glenstone Avenue to Route 60 CLOSED
-
Route 60 crossovers CLOSED between Route 65 and Greene County Routes NN/J
-
September 15-November 1
-
Nighttime lane closings for shoulder construction/guardrail/striping/pavement smoothing
-
Prime Contractor:Emery Sapp and Sons, Inc. of Columbia
-
Completion Date:November 2019 (However, contractor plans to complete project by late September.)
-
Total Project Cost:$8.1 million
|